EPCM Off Site Fresh Water Collection and Pumping system for the Caserones Mining Project.

PROJECT DESCRIPTION

An EPCM Professional Services Contract which involved carrying out Detailed Engineering and Construction Procurement and Administration, including Testing and the transfer for Commissioning.

The project involved the construction and testing of the Fresh Water Supply System, in API quality carbon steel pipes. The system was 37km long and included water intake wells, pump stations, a Tap-Off Substation and 23kV power lines with an automatic, fiber optic Operation and Control System.
 

  • Client

    SCM Minera Lumina Cooper Chile

  • Location

    Tierra Amarilla district, Copiapó, Atacama Region

  • Amount

     14,535,012 USD

  • Estimated project investment

    420 MM USD

  • Duration

     1st of December 2011 to the 1st of June 2014

Value

Proposition

R&Q committed to carrying out effective and efficient administration of the construction contracts, including the Detailed Engineering and the Procurement management, in order to meet the cost, term, safety and environmental objectives of the Project as well as to guarantee the system capacity and its future expansion in the context of a facility outside the area of the main project, inserted in the valley and community.